M14 - Spirent - Verify Re-Write C-VID Downstream

Test Objective

  • The Purpose of this test is to verify ONU can re-write single C-VID frames as priority tagges frames in downstream towards RG

Test Configuration

  • Test Setup as shown in Section – 7
  • Maple OLT and ONU is activated using VOLTHA
  • Provision HSIA/unicast service on the OLT and connected ONU from VOLTHA

Test Procedure

Pass/Fail Criteria